โ Recently achieved construction milestones include conditioned air for finishes (from temporary) and building watertight. ๐ As summer winds down, so does the resource curve, slowing decreasing from peak levels since spring. ๐ข This 240,000 SF higher education research facility in Baltimore, MD includes seven (7) levels with a single-level parking garage below, and mechanical penthouse above. ๐ Anticipated final completion of Summer 2027.